Portable Crushing

Project: Portable Crushing Operation
Client: Range Government to privates
Project Location: Majority of Projects are located in Southern Ontario
Construction Period: Year round capability
Project Description:

Hard Rock Group’s portable crushing operation has taken on projects throughout southern Ontario. Working for a range of cliental, from Municipal bid contracts, to private customer, to inhouse crushing, Hard Rock has successfully completed projects for over 20 years of various sizes from 10,000 tonnes to 100,000 tonnes.
The Hard Rock Group looks forward to completing your crushing requirements.

 

Project: Hwy 417 Southeast of Ottawa Material removal and blending for reuse

Client: Dufferin Const.
Engineer: Ministry of Transportation
Contract Value: 1.2 million
Project Location: Hwy 417 between Ottawa and L’Original
Construction Period: June 2004 - Aug 2005
Project Description:

Mill and screen project.
The road structure consisted 150 mm of hot mix and approx. 300 mm of cement treated base. The salvaged materials was screened and blended, creating a modified granular B. Total of 250,000 tonnes were processed over the two year project.